Ahead September increased load-shedding plans, ZESCO reports progress on power projects

0

As ZESCO prepares to start implementing the planned increased load-shedding schedule next month, the power utility firm has provided updates on several key power projects aimed at alleviating the country’s electricity deficit.

During the Energy Forum for Africa in Lusaka, ZESCO Chief Engineer (Research), Kabwe Mulenga, detailed the progress of initiatives including the 789 megawatts (MW) Luapula hydropower project, the 244MW Kalungwishi River hydropower project and the upgrade of the Chishimba hydropower project.

For the Luapula hydropower project, Mulenga noted that the Multilateral Cooperation Centre for Development Finance (MCDF) had committed US$4.2 million for feasibility and Social Impact Assessment (ESIA) studies through the African Development Bank.

However, there remained a funding gap of US$1.9 million for the ESIA and feasibility studies, with an additional US$2 million needed for structuring and transaction support.

Read more: Govt says load-shedding to last till December, blames electricity misuse for worsening power cuts

The project, located on the Luapula River, aims to develop hydropower plants and transmission lines at three sites, with a total installed capacity of 789 MW and an estimated annual generation of 3,878 GWh.

The total capital expenditure is projected at US$1.7 billion.

Regarding the 244MW Kalungwishi River hydropower project, ZESCO says it is in the process of securing an equity partner.

The feasibility study had been completed, with an estimated construction cost of US$886 million, including power evacuation.

The ESIA report had already been submitted to the Zambia Environmental Management Agency (ZEMA).

Mulenga also provided updates on the Chishimba hydropower project, which currently has an installed capacity of six megawatts but operates at three megawatts due to outdated equipment.

A consultant for tender preparation and supervision has been procured, and ZESCO is finalizing the specifications and tender documents for the upgrade.

WARNING! All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express permission from ZAMBIA MONITOR.

Government commits to overhauling railway infrastructure

Previous article

UKA asks Hichilema to despatch ex-president Lungu to Zimbabwe in bid to resolve diplomatic face-off

Next article

You may also like

Comments

Leave a reply

Your email address will not be published. Required fields are marked *

More in Economy